10/06/2026
Rough seas have hindered Mohawk Northeast but the work on the new spur jetty is making progress. Both barges are now back at the jetty after taking refuge up river from storms that roiled ocean waters. There are two barges filled with rocks moored near Eagle Island.
From U.S. Army Corps of Engineers Project Manager Jen Thalhauser: "Our jetty construction continues to advance on schedule, with the project successfully hitting several key milestones. Approximately 500 feet of marine mattress have been successfully placed, and nearly 9,000 tons of stone have been delivered to the site. Construction is moving forward steadily, with nearly 100 feet of the total 750-foot spur jetty now completed. Additionally, representatives from the U.S. Army Corps of Engineers (USACE) visited the site last Thursday to review the project's progress. Mohawk will maintain its active operations on-site until winter weather conditions present a sustained safety or construction concern."