06/04/2026
🌊 Shoreline Reconfiguration Project Update 🌊
We are officially on Phase 6 of the shoreline reconfiguration project! 🎉
The new water inflatables were delivered by semi today, bringing us one step closer to the finish line!
✅ Phase 1: New seasonal boat dock
✅ Phase 2: New power installation with full services to both new seasonal and to the cabin/visitor dock
✅ Phase 3: New boat launch with 12 ft pads & crushed concrete road.
✅ Phase 4: New sand beach, Adirondack chairs,kayaks, paddle boards
✅ Phase 5: Temporary dock built from the old dock
🚧 Phase 6: Cabin dock and visitor dock construction (about halfway complete – remaining sections arrive in a couple of weeks)
Coming Next:
🔹 Phase 7: Complete the new visitor and cabin docks
🔹 Phase 8: Remove the old wooden temporary dock
🔹 Phase 9: Install the new water park where the temporary dock is currently located! 🌊🏖️
🔹 Phase 10: end of September build new fish cleaning house!!!
It’s exciting to see this project coming together phase by phase. Thanks to everyone following along and supporting the improvements! More updates coming soon as we continue transforming the shoreline! 🚤☀️🏖️