ADOT
There are NO CLOSURES scheduled on US 60 between Superior and Miami April 27 - May 1!
In fact, these closures for the Queen Creek and Waterfall Canyon Bridge project are going to be more intermittent going forward. This means fewer restrictions each week!
The project recently hit the halfway mark. Work continues now on the Queen Creek Bride's lower structure, with bridge girder and deck construction expected to begin in spring 2027.
So from here out we will only be posting when there are upcoming restrictions. So if you don't hear from us, assume there are none planned.